ESS construction of private sector in 2020

Vizenviztro no.1 and 12 other places (Cheorwon and Gongju, 95MWh)

  • Construction details: Construction details: Install ESS in solar power plant and give REC weight to electricity discharged through ESS
  • Install ESS in Vizenviztro no.1 and 12 other places picture
  • Install ESS in Vizenviztro no.1 and 12 other places picture

Solarbank and 2 other places (Goheung, 8.2MWh)

  • Construction details: Construction details: Install ESS in solar power plant and give REC weight to electricity discharged through ESS
  • Install ESS in Solarbank and 2 other places picture
  • Install ESS in Solarbank and 2 other places places picture

ESS construction of private sector in 2018

Kumkang No. 1 solar power plant (Goseong, 7MWh)

  • Construction details: Install ESS in solar power plant and give REC weight 5.0 to electricity discharged through ESS
  • Install ESS in Kumkang No. 1 solar power plant picture
  • Install ESS in Kumkang No. 1 solar power plant picture

ESS construction of private sector in 2017

Kumkang No. 2 solar power plant (Goseong, 7MWh)

  • Construction details: Install ESS in solar power plant and give REC weight 5.0 to electricity discharged through ESS
  • Install ESS in Kumkang No. 2 solar power plant picture
  • Install ESS in Kumkang No. 2 solar power plant picture

Solar power plant (3.3MWh) in Maesan (Cheongyang), Right Light (Iksan) and East Sea (Haenam)

  • Construction details: Install ESS in solar power plant and give REC weight 5.0 to electricity discharged through ESS
  • Install ESS in Solar power plant (3.3MWh) in Maesan (Cheongyang) picture
  • Install ESS in Solar power plant (3.3MWh) in Maesan (Cheongyang) picture